NPRR264
| Title: |
Clarification of Nodal Protocol Requirements for Generators With Multiple Points of Interconnection
|
| Next Group: |
|
| Next Step: |
|
| Status: |
Approved
on 06/21/2011
|
| Effective Date: |
07/01/2011
|
| Date |
Gov Body |
Motion |
Result |
Against |
Abstentions |
|
06/21/2011
|
Board of Directors
|
To approve NPRR264 as recommended by TAC in the 5/5/11 TAC Report.
|
Passed
|
|
|
|
05/05/2011
|
TAC
|
To recommend approval of NPRR264 as recommended by PRS in the 4/21/11 PRS Report.
|
Passed
|
0
|
0
|
|
04/21/2011
|
PRS
|
To endorse and forward the 3/24/11 PRS Report and Impact Analysis for NPRR264 to TAC.
|
Passed
|
0
|
0
|
|
03/24/2011
|
PRS
|
To recommend approval of NPRR264 as amended by the 1/11/11 ERCOT comments and as revised by PRS.
|
Passed
|
0
|
1 IOU
|
|
02/17/2011
|
PRS
|
To table NPRR264 for one month.
|
Passed
|
0
|
0
|
|
01/20/2011
|
PRS
|
To table NPRR264 for one month.
|
Passed
|
0
|
0
|
|
12/16/2010
|
PRS
|
To table NPRR264 for one month.
|
Passed
|
0
|
0
|
|
11/18/2010
|
PRS
|
To table NPRR264 for one month.
|
Passed
|
0
|
0
|
|
10/21/2010
|
PRS
|
To table NPRR264 for one month.
|
Passed
|
0
|
0
|
|
09/23/2010
|
PRS
|
To table NPRR264 and to request that the ERCOT CEO reevaluate whether NPRR264 is needed prior to the Texas Nodal Market Implementation Date.
|
Passed
|
0
|
1 Ind Gen
|
|
08/19/2010
|
PRS
|
To table NPRR264 for one month.
|
Passed
|
0
|
0
|
Vote tallies here reflect individual votes, not the weight of the votes by market segment. Affirmative votes are not recorded in these vote tallies. For additional details on the voting record, please consult the Recommendation or Action Report, or the official vote tally if available, as posted in the key documents.
| Status: |
Approved
|
| Date Posted: |
08/12/2010
|
| Sponsor: |
WMS
|
| Urgent: |
No
|
| Sections: |
1.6.5, 2.1
|
| Description: |
This Nodal Protocol Revision Request (NPRR) adds language to specify that for a new Point of Interconnection (POI), Generation Resources must comply with provisions of Other Binding Documents (OBDs), Section 3.15, Voltage Support, and Nodal Operating Guide Section 2.9, Voltage Ride-Through Requirements for Generation Resources, based upon the execution date of the most recent Standard Generation Interconnection Agreement (SGIA). For existing Generation Resources with more than one POI, compliance with these requirements is based on the execution of the SGIA relative to the POI where the Generation Resource is electrically connected. This NPRR also revises the definition of POI to clarify that the POI is determined by the voltage level and substation, rather than the location, of the relevant interconnection.
|
| Reason: |
Some Nodal Protocol requirements applicable to Generation Resources are based upon the date of execution of the SGIA between the Resource owner and the Transmission Service Provider (TSP). For Resources with more than one POI, the question arises which SGIA date should be used to determine applicability of such requirements to the Resource. The Multiple Interconnections for Generators Task Force (MIGTF) recommended that the date of the original SGIA be binding for this purpose. The MIGTF recommendation was endorsed by the Reliability and Operations Subcommittee (ROS), Wholesale Market Subcommittee (WMS), and Technical Advisory Committee (TAC). This NPRR clarifies which Nodal Protocol and OBD requirements are applicable to an existing Generation Resource’s new or multiple POIs.
|
-
(08/12/10, .doc, 84.5 KB)
-
(08/12/10, .doc, 68.5 KB)
-
(08/18/10, .doc, 40 KB)
-
(08/23/10, .doc, 90.5 KB)
-
(09/22/10, .doc, 39.5 KB)
-
(09/27/10, .doc, 92.5 KB)
-
(09/29/10, .doc, 71 KB)
-
(10/25/10, .doc, 93 KB)
-
(11/19/10, .doc, 95 KB)
-
(12/20/10, .doc, 95.5 KB)
-
(01/11/11, .doc, 42 KB)
-
(01/24/11, .doc, 87.5 KB)
-
(02/03/11, .doc, 46 KB)
-
(02/21/11, .doc, 90.5 KB)
-
(03/21/11, .doc, 52 KB)
-
(03/28/11, .doc, 93 KB)
-
(04/07/11, .doc, 56.5 KB)
-
(04/22/11, .doc, 94 KB)
-
(05/09/11, .doc, 95.5 KB)
-
(06/22/11, .doc, 96.5 KB)